A Development Model for Identifying the Uncertainty Sources and Their Impacts on Bridge Construction Projects
DOI:
https://doi.org/10.7250/bjrbe.2023-18.592Keywords:
bridge construction project, GSAHP, spherical fuzzy set, uncertaintyAbstract
Bridge construction projects are rife with uncertainty because of their unique features, from execution of the work, time estimation, inspection and assessment to fund allocation. Therefore, a critical step is recognise and categorise the uncertainties associated in bridge building in order to meet project objectives in terms of quality, cost, schedule, environmental, safety, and technical indicators. Various models, however, have been created to detect and prioritise the uncertainty. One of the most commonly used approaches for dealing with uncertainty is the spherical fuzzy set. To formulate an issue, this technique uses a mathematical procedure. The analytic hierarchy process (AHP), on the other hand, is a computer technique that solves a complicated problem by breaking it down into numerous basic problems. A hybrid model based on spherical fuzzy sets and AHP (SAHP) can benefit from both approaches. This study proposes a SAHP based on group decision making (GSAHP) to prioritise the sources of uncertainty in bridge construction projects. Likewise, a modified algorithm is proposed for checking the consistency of the spherical fuzzy matrices. To show the model potential, a real case study is illustrated and evaluated. The model demonstrates its capabilities in modelling uncertainty under an environment with a number of unknown components. The findings reveal that the “delays” factor is of the highest, and the “project team conflicts” parameter is of the least importance. The research findings could be used by decision makers and managers to develop preventive measures.References
Adeli, H., & Karim, A. (1997). Scheduling/cost optimization and neural dynamics model for construction. Journal of Construction Engineering and Management, 123(4), 450–458. https://doi.org/10.1061/(ASCE)0733-9364(1997)123:4(450)
Ahadian, B., Veisy, O., & Azizi, V. (2016). A multi-objective stochastic programming approach for project time, cost and quality trade-off problem (TCQTP). Jordan Journal of Civil Engineering, 10(4), 553–563. https://jjce.just.edu.jo/issues/paper.php?p=3718.pdf
Akintoye, A. S., & MacLeod, M. J. (1997). Risk analysis and management in construction. International Journal of Project Management, 15(1), 31–38. https://doi.org/10.1016/S0263-7863(96)00035-X
Akram, M. (2021). Decision making method based on spherical fuzzy graphs. In C. Kahraman & F. Kutlu Gündoğdu (Eds.), Decision making with spherical fuzzy sets, studies in fuzziness and soft computing, 392, (pp. 153–197). Springer Cham. https://doi.org/10.1007/978-3-030-45461-6_7
Alkhaleel, B. A., Liao, H., & Sullivan, K. M. (2022). Risk and resilience-based optimal post-disruption restoration for critical infrastructures under uncertainty. European Journal of Operational Research, 296(1), 174–202. https://doi.org/10.1016/j.ejor.2021.04.025
AMR. (2020). Bridge construction market by type (beam bridge, truss bridge, arch bridge, suspension bridge, cable-stayed bridge, and others), material (steel, concrete, and composite materials), and application (road & highway and railway): Global opportunity analysis and industry forecast, 2020–2027. Allied Market Research. https://www.reportlinker.com/p05955109/Bridge-Cons¬truction-Market-by-Type-Material-and-Application-Global-Opportunity- Analysis-and-Industry-Forecast-.html
Antunes, R., & Gonzalez, V. (2015). A production model for construction: A theoretical framework. Buildings, 5(1), 209–228. https://doi.org/10.3390/buildings5010209
Asadi, P., Rezaeian Zeidi, J., Mojibi, T., Yazdani-Chamzini, A., & Tamošaitienė, J. (2018). Project risk evaluation by using a new fuzzy model based on ELENA guideline. Journal of Civil Engineering and Management, 24(4), 284–300. https://doi.org/10.3846/jcem.2018.3070
Ashraf, S., Abdullah, S., Mahmood, T., Ghani, F., & Mahmood, T. (2019). Spherical fuzzy sets and their applications in multi-attribute decision making problems. Journal of Intelligent & Fuzzy Systems, 36(3), 2829–2844. https://doi.org/10.3233/JIFS-172009
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International Journal of Project Management, 24(4), 349–357. https://doi.org/10.1016/j.ijproman.2005.11.010
Atanassov, K. T. (1986). Intuitionistic fuzzy sets. Fuzzy Sets and Systems, 20(1), 87–96. https://doi.org/10.1016/S0165-0114(86)80034-3
Aziz, R. F., & Abdel-Hakam, A. A. (2016). Exploring delay causes of road construction projects in Egypt. Alexandria Engineering Journal, 55(2), 1515–1539. https://doi.org/10.1016/j.aej.2016.03.006
Baccarini, D. (2019). Project uncertainty management. https://www.researchgate.net/project/Project-Uncertainty-Management
Bahamid, R. A., & Doh, S. I. (2017). A review of risk management process in construction projects of developing countries. IOP Conf. Series: Materials Science and Engineering, Johor Bahru, Malaysia, 271, Article 012042. https://doi.org/10.1088/1757-899X/271/1/012042
Banaitiene, N., & Banaitis, A. (2012). Risk management in construction projects. In N. Banaitiene (Ed.), Risk management – Current issues and challenges, IntechOpen. https://doi.org/10.5772/51460
Bingol, B. N., & Polat, G. (2015). Time-cost-quality trade-off model for subcontractor selection using discrete particle swarm optimization algorithm. In A. B. Raidén, & E. Aboagye-Nimo (Eds.), Proceedings of 31st Annual ARCOM Conference, Lincoln, UK, Association of Researchers in Construction Management, 13–22.
Carr, V., & Tah, J. H. M. (2001). A fuzzy approach to construction project risk assessment and analysis: construction project risk management system. Advances in Engineering Software, 32(10–11), 847–857. https://doi.org/10.1016/S0965-9978(01)00036-9
Cheng, M. Y., & Tran, D. H. (2015). Opposition-based multiple-objective differential evolution to solve the time-cost-environment impact trade-off problem in construction projects. Journal of Computing in Civil Engineering, 29(5), Article 04014074. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000386
Choi, B. C., & Park, M. J. (2019). A linear time-cost tradeoff problem with multiple interim assessments within multiple projects in parallel. Computers & Industrial Engineering, 128, 651–658. https://doi.org/10.1016/j.cie.2019.01.003
Cuong, B. C. (2014). Picture fuzzy sets. Journal of Computer Science and Cybernetics, 30(4), 409–420. https://doi.org/10.15625/1813-9663/30/4/5032
Cuong, B. C., & Kreinovich, V. (2013). Picture fuzzy sets-a new concept for computational intelligence problems. Proceedings of 2013 3rd World Congress on Information and Communication Technologies (WICT 2013), Hanoi, Vietnam, 1–6. https://doi.org/10.1109/WICT.2013.7113099
Dubois, A., & Gadde, L. E. (2002). The construction industry as a loosely coupled system: Implications for productivity and innovation. Construction Management and Economics, 20(7), 621–631. https://doi.org/10.1080/01446190210163543
Elhag, T. M., & Wang, Y. M. (2007). Risk assessment for bridge maintenance projects: Neural networks versus regression techniques. Journal of Computing in Civil Engineering, 21(6), 402–409. https://doi.org/10.1061/(ASCE)0887-3801(2007)21:6(402)
El-Karim, M. S. B. A. A., Nawawy, O. A. M. E., & Abdel-Alim, A. M. (2017). Identification and assessment of risk factors affecting construction projects. HBRC Journal, 13(2), 202–216. https://doi.org/10.1016/j.hbrcj.2015.05.001
Flyvbjerg, B. (2007). Policy and planning for large-infrastructure projects: Problems, causes, cures. Environment and Planning B: Planning & Design, 34(4), 578–597. https://doi.org/10.1068/b32111
Fouladgar, M. M., Yazdani-Chamzini, A., & Zavadskas, E. K. (2012). Risk evaluation of tunneling projects. Archives of Civil and Mechanical Engineering, 12(1), 1–12. https://doi.org/10.1016/j.acme.2012.03.008
Garibaldi, J. M., & Ozen, T. (2007). Uncertain fuzzy reasoning: a case study in modelling expert decision making. IEEE Transactions on Fuzzy Systems, 15(1), 16–30. https://doi.org/10.1109/TFUZZ.2006.889755
Gau, W. L., & Buehrer, D. J. (1993). Vague sets. IEEE Transactions on Systems, Man, and Cybernetics, 23(2), 610–614. https://doi.org/10.1109/21.229476
Ghousi, R., Khanzadi, M., & Mohammadi Atashgah, K. (2018). A flexible method of building construction safety risk assessment and investigating financial aspects of safety program. International Journal of Optimization in Civil Engineering, 8(3), 433–452. http://ijoce.iust.ac.ir/article-1-354-en.html
Gimsing, N. J., & Georgakis, C. T. (2012). Cable supported bridges: Concept and design (3rd ed.). John Wiley & Sons, Ltd. https://doi.org/10.1002/9781119978237
Gosling, J., Naim, M., & Towill, D. (2012). Identifying and categorizing the sources of uncertainty in construction supply chains. Journal of Construction Engineering and Management, 139(1), 102–110. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000574
Gündoğdu, F. K., & Kahraman, C. (2019). Spherical fuzzy sets and spherical fuzzy TOPSIS method. Journal of Intelligent & Fuzzy Systems, 36(1), 337–352. https://doi.org/10.3233/JIFS-181401
Gündoğdu, F. K., & Kahraman, C. (2021). Optimal site selection of electric vehicle charging station by using spherical fuzzy TOPSIS method. In C. Kahraman, & F.K. Gündoğdu (Eds.), Decision making with spherical fuzzy sets: Theory and applications (pp. 201–216), 392, Springer, Cham. https://doi.org/10.1007/978-3-030-45461-6_8
Hoang, N. D., Nguyen, Q. L., & Pham, Q. N. (2015). Optimizing construction project labor utilization using differential evolution: A comparative study of mutation strategies. Advances in Civil Engineering, 2015, Article 108780. https://doi.org/10.1155/2015/108780
Hosseinzadeh, F., Paryzad, B., Shahsavari-Pour, N., & Najafi, E. (2020). Fuzzy combinatorial optimization in four-dimensional tradeoff problem of cost-time-quality-risk in one dimension and in the second dimension of risk context in ambiguous mode. Engineering Computations, 37(6), 1967–1991. https://doi.org/10.1108/EC-03-2019-0094
PlanRadar. (2021). 7 major risks in construction projects and how to avoid them. https://www.planradar.com/builders-risk/
Iqbal, S., Choudhry, R. M., Holschemacher, K., Ali, A., & Tamošaitienė, J. (2015). Risk management in construction projects. Technological and Economic Development of Economy, 21(1), 65–78. https://doi.org/10.3846/20294913.2014.994582
Kahraman, C., & Gündoğdu, F. K. (2018). From 1D to 3D membership: spherical fuzzy sets. BOS/SOR2018 Conference, Warsaw, Poland. https://acikerisim.iku. edu.tr/entities/publication/b3a66341-8c8d-4177-abd5-037b1be16872
Kannimuthu, M., Raphael, B., Palaneeswaran, E., & Kuppuswamy, A. (2019). Optimizing time, cost and quality in multi-mode resource-constrained project scheduling. Built Environment Project and Asset Management, 9(1), 44–63. https://doi.org/10.1108/BEPAM-04-2018-0075
Karasan, A., Boltürk, E., & Gündogdu, F. K. (2021). Assessment of livability indices of suburban places of Istanbul by using spherical fuzzy CODAS method. In C. Kahraman, & F.K. Gündoğdu (Eds.), Decision making with spherical fuzzy sets: Theory and applications (pp. 277–293), 392, Springer, Cham. https://doi.org/10.1007/978-3-030-45461-6_12
Katrekar, S., Magar, R. B., & Khan, A. N. (2018). Review on simulating uncertainties in construction projects. Conference on Advances in Civil Engineering 2018 (CACE-2018), Thakur College of Engineering and Technology, Thakur, 5(3), 86–89. http://ir.aiktclibrary.org:8080/xmlui/handle/123456789/2850
Leu, S. S., & Yang, C. H. (1999). GA-based multicriteria optimal model for construction scheduling. Journal of Construction Engineering and Management, 125(6), 420–427. https://doi.org/10.1061/(ASCE)0733-9364(1999)125:6(420)
Leyman, P., Driessche, N. V., Vanhoucke, M., & Causmaecker, P. D. (2019). The impact of solution representations on heuristic net present value optimization in discrete time/cost trade-off project scheduling with multiple cash flow and payment models. Computers and Operations Research, 103, 184–197. https://doi.org/10.1016/j.cor.2018.11.011
Liu, D., Li, H., Wang, H., Qi, C., & Rose, T. (2020). Discrete symbiotic organisms search method for solving large-scale time-cost trade-off problem in construction scheduling. Expert Systems with Applications, 148, Article 113230. https://doi.org/10.1016/j.eswa.2020.113230
Liu, L., Burns, S. A., & Feng, C. W. (1995). Construction time-cost trade-off analysis using LP/IP hybrid method. Journal of Construction Engineering and Management, 121(4), 446–454. https://doi.org/10.1061/(ASCE)0733-9364(1995)121:4(446)
Lu, Q., Won, J., & Cheng, J. C. P. (2016). A financial decision making framework for construction projects based on 5D Building Information Modeling (BIM). International Journal of Project Management, 34(1), 3–21. https://doi.org/10.1016/j.ijproman.2015.09.004
Luong, D. L., Tran, D. H., & Nguyen, P. T. (2018). Optimizing multi-mode time-cost-quality trade-off of construction project using opposition multiple objective difference evolution. International Journal of Construction Management, 21(3), 271–283. https://doi.org/10.1080/15623599.2018.1526630
Mahmood, T., Ullah, K., Khan, Q., & Jan, N. (2019). An approach toward decision-making and medical diagnosis problems using the concept of spherical fuzzy sets. Neural Computing and Applications, 31, 7041–7053. https://doi.org/10.1007/s00521-018-3521-2
Maleki, S. (2013). Bridge engineering in Iran. In W.F. Chen, & L. Duan (Eds.), Handbook of international bridge engineering (1st ed.), Taylor & Francis Group, LLC.
McManus, N., & Haddad, A. N. (2014). Incident records: Understanding the past to prevent future hazardous energy incidents. Professional Safety, 59(12), 34–43. https://www.researchgate.net/publication/273259459_Incident_Records_Understanding_the_Past_to_Prevent_Future_Hazardous_Energy_ Incidents
Moghayedi, A., & Windapo, A. (20190. Key uncertainty events impacting on the completion time of highway construction projects. Frontiers of Engineering Management, 6(2), 275–298. https://doi.org/10.1007/s42524-019-0022-7
Mohammadi Atashgah, K., Ghousi, R., Monir Abbasi, A., & Tayefi Nasrabadi, A. (2022). Developing a model for time-cost trade-off optimization problem considering overdraft issue in uncertain environments, Journal of Industrial and Systems Engineering, 14(3), 259–279. http://www.jise.ir/article_154961.html
Moret, Y., & Einstein, H. H. (2016). Construction cost and duration uncertainty model: Application to high-speed rail line project. Journal of Construction Engineering and Management, 142(10), Article 05016010. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001161
Naderpour, A., Sardroud, J. M., Mofid, M., Xenidis, Y., & Rostam, T. P. (2019). Uncertainty management in time estimation of construction projects: A systematic literature review and new model development. Scientia Iranica, 26(2), 752–778. http://scientiairanica.sharif.edu/article_4605_9a62e0947df e3d512e7b9503fc9710ae.pdf
Nibbelink, J. G., Sutrisna, M., & Zaman, A. U. (2017). Unlocking the potential of early contractor involvement in reducing design risks in commercial building refurbishment projects – A Western Australian perspective. Architectural Engineering and Design Management, 13(6), 439–456. https://doi.org/10.1080/17452007.2017.1348334
Ning, X., & Lam, K. C. (2013). Cost-safety trade-off in unequal-area construction site layout planning. Automation in Construction, 32, 96–103. https://doi.org/10.1016/j.autcon.2013.01.011
Odediran, S. J., & Windapo A. O. (2018). Risk-based entry decision into African construction markets: A proposed integrated model. Built Environment Project and Asset Management, 8(1), 91–111. https://doi.org/10.1108/BEPAM-05-2016-0021
Orm, M. B., & Jeunet, J. (2018). Time cost quality trade-off problems: A survey exploring the assessment of quality. Computers & Industrial Engineering, 118, 319–328. https://doi.org/10.1016/j.cie.2018.01.012
Padalkar, M., & Gopinath, S. (2016). Are complexity and uncertainty distinct concepts in project management? A taxonomical examination from literature. International Journal of Project Management, 34(4), 688–700. https://doi.org/10.1016/j.ijproman.2016.02.009
Panwar, A., & Jha, K. N. (2019). A many-objective optimization model for construction scheduling. Construction Management and Economics, 37(12), 727–739. https://doi.org/10.1080/01446193.2019.1590615
Pawlak, Z. (1982). Rough sets. International Journal of Computer & Information Sciences, 11(5), 341–356. https://doi.org/10.1007/BF01001956
Perminova, O. (2011). Managing uncertainty in projects. Abo Akademi University Press: Turku, Finland. https://www.doria.fi/bitstream/handle/10024/69174/perminova_olga.pdf
Rabbani, A., Zamani, M., Yazdani-Chamzini, A., & Zavadskas, E. K. (2014). Proposing a new integrated model based on sustainability balanced scorecard (SBSC) and MCDM approaches by using linguistic variables for the performance evaluation of oil producing companies. Expert Systems with Applications, 41(16), 7316–7327. https://doi.org/10.1016/j.eswa.2014.05.023
Ramasesh, R. V., & Browning, T. R. (2014). A conceptual framework for tackling knowable unknown unknowns in project management. Journal of Operations Management, 32(4), 190–204. https://doi.org/10.1016/j.jom.2014.03.003
Ranasinghe, U., Jefferies, M., Davis, P., & Pillay, M. (2021). Conceptualising project uncertainty in the context of building refurbishment safety: A systematic review. Buildings, 11(3), Article 89. https://doi.org/10.3390/buildings11030089
Saaty, T. L. (1980). The analytic hierarchy process. McGraw-Hill, New York.
Schieg, M. (2006). Risk management in construction project management. Journal of Business Economics and Management, 7(2), 77–83. https://doi.org/10.3846/16111699.2006.9636126
Sharaf, I. M. (2021). Global supplier selection with spherical fuzzy analytic hierarchy process. In C. Kahraman, & F.K. Gündoğdu (Eds.), Decision making with spherical fuzzy sets: Theory and applications (pp. 323–348), 392, Springer, Cham. https://doi.org/10.1007/978-3-030-45461-6_14
Smarandache, F. (1998). Neutrosophy: neutrosophic probability, set, and logic: analytic synthesis & synthetic analysis. Rehoboth, NM: American Research Press
Szymański, P. (2017). Risk management in construction. Procedia Engineering, 208, 174–182. https://doi.org/10.1016/j.proeng.2017.11.036
Tercan, M. (2019). The Rumsfeld matrix: A model to estimate uncertainty in projects. https://melvintercan.com/blog/the-rumsfeld-matrix-uncertainty.html
Torra, V., & Narukawa, Y. (2009). On hesitant fuzzy sets and decision. 2009 International Conference on Fuzzy Systems, Jeju, Korea (South), 1378–1382. https://doi.org/10.1109/FUZZY.2009.5276884
Tran, D. H., Cheng, M. Y., & Prayogo, D. (2016). A novel Multiple Objective Symbiotic Organisms Search (MOSOS) for time-cost-labor utilization trade off problem. Knowledge-Based Systems, 94, 132–145. https://doi.org/10.1016/j.knosys.2015.11.016
Tran, D. H., & Long, L. D. (2018). Project scheduling with time, cost and risk trade-off using adaptive multiple objective differential evolution. Engineering, Construction and Architectural Management, 25(5), 623–638. https://doi.org/10.1108/ECAM-05-2017-0085
Tran, D. H., Luong, D. L., Duong, M. T., Le, T. N., & Pham, A. D. (2017). Opposition multiple objective symbiotic organisms search (OMOSOS) for time, cost, quality and work continuity tradeoff in repetitive projects. Journal of Computational Design and Engineering, 5(2), 160–172. https://doi.org/10.1016/j.jcde.2017.11.008
Valk, G., & Goldbach, O. (2021). Towards a robust β research design: on reasoning and different classes of unknowns. Journal of Intelligence History, 20(1), 72–87. https://doi.org/10.1080/16161262.2020.1746144
Vejrum, T., & Nielsen, L. L. (2014). Cable-stayed bridges (chapter 10). In Bridge engineering handbook (2nd ed.), CRC Press, Taylor & Francis Group.
Ward, S., & Chapman, C. (2008). Stakeholders and uncertainty management in projects. Construction Management and Economics, 26(6), 563–577. https://doi.org/10.1080/01446190801998708
Weishaar, C. (2018). Predicting the impact of resource delays on a construction project’s critical path using Monte Carlo simulation [Master Thesis, University of Arkansas]. http://scholarworks.uark.edu/etd/2657
Wood, H., & Ashton, P. (2009). Factors of complexity in construction projects. Proceedings of the 25th Annual ARCOM Conference, Nottingham, UK.
Xu, Z., & Liao, H. (2014). Intuitionistic fuzzy analytic hierarchy process. IEEE Transactions on Fuzzy Systems, 22(4), 749–761. https://doi.org/10.1109/TFUZZ.2013.2272585
Yacob, R. I., Rahmat, I., Saruwono, M., & Ismail, Z. (2017). Effects of uncertainty factors and refurbishment projects performance in relation to leadership quality of project managers. Journal of Building Performance, 8(1), 69–79. https://www.researchgate.net/publication/321300521_Effects_of_Uncertainty_Factors_and_Refurbishment_Projects_Performance_In_Relation_To_Leadership_Quality_of_Project_Managers
Yager, R. R. (2013). Pythagorean fuzzy subsets. 2013 Joint IFSA World Congress and NAFIPS Annual Meeting (IFSA/NAFIPS), Edmonton, AB, Canada, 57–61. https://doi.org/10.1109/IFSA-NAFIPS.2013.6608375
Yager, R. R. (2016). Generalized orthopair fuzzy sets. IEEE Transactions on Fuzzy Systems, 25(5), 1222–1230. https://doi.org/10.1109/TFUZZ.2016.2604005
Yager, R. R., & Abbasov, A. M. (2013). Pythagorean membership grades, complex numbers, and decision making. International Journal of Intelligent Systems, 28(5), 436–452. https://doi.org/10.1002/int.21584
Yang, I. T., Lin, Y. C., & Lee, H. Y. (2014). Use of support vector regression to improve computational efficiency of stochastic time-cost trade-off. Journal of Construction Engineering and Management, 140(1), Article 04013036. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000784
Yazdani, M., Alidoosti, A., & Zavadskas, E. K. (2011). Risk analysis of critical infrastructures using fuzzy copras. Economic Research, 24(4), 27–40. https://doi.org/10.1080/1331677X.2011.11517478
Yazdani-Chamzini, A. (2014a). An integrated fuzzy multi criteria group decision making model for handling equipment selection. Journal of Civil Engineering and Management, 20(5), 660–673. https://doi.org/10.3846/13923730.2013.802714
Yazdani-Chamzini, A., (2014b). Proposing a new methodology based on fuzzy logic for tunnelling risk assessment. Journal of Civil Engineering and Management, 20(1), 82–94. https://doi.org/10.3846/13923730.2013.843583
Yazdani-Chamzini, A., Yakhchali, S. H., & Mahmoodian, M. (2013). Risk ranking of tunnel construction projects by using the ELECTRE technique under a fuzzy environment. International Journal of Management Science and Engineering Management, 8(1), 1–14. https://doi.org/10.1080/17509653.2013.783185
Zadeh, L. A. (1965). Fuzzy sets. Information and Control, 8(3), 338–353. https://doi.org/10.1016/S0019-9958(65)90241-X
Zadeh, L. A. (1975). The concept of a linguistic variable and its application to approximate reasoning. Information Sciences, 8(3), 199–249. https://doi.org/10.1016/0020-0255(75)90036-5
Zheng, E. Z. H., & Carvalho, M. M. (2016). Managing uncertainty in projects: a review, trends and gaps. Revista de Gestão e Projetos –GeP, 7(2), 95–109. https://dialnet.unirioja.es/servlet/articulo?codigo=5757397
Zheng, H. (2017). The bi-level optimization research for time-cost-quality-envi¬ronment trade-off scheduling problem and its application to a construction project. Proceedings of the Tenth International Conference on Management Science and Engineering Management, Advances in Intelligent Systems and Computing, 502. https://doi.org/10.1007/978-981-10-1837-4_62
Zou, X., Fang, S. C., Huang, Y. S., & Zhang, L. H. (2017). Mixed-integer linear programming approach for scheduling repetitive projects with time-cost trade-off consideration. Journal of Computing in Civil Engineering, 31(3), Article 06016003. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000641
Downloads
Published
Issue
Section
License
Copyright (c) 2023 Kayvan Mohammadi Atashgah, Rouzbeh Ghousi, Armin Monir Abbasi, Abbasali Tayefi Nasrabadi
This work is licensed under a Creative Commons Attribution 4.0 International License.